Renovations are underway at the Bangs Community Center at 70 Boltwood Walk. The project includes health and safety upgrades such as a new sprinkler system, electrical and HVAC improvements, and full ADA accessibility. The building will remain open during construction, though certain sections will be temporarily closed. The project is funded by $2.8 million in federal ARPA funds and is expected to be complete in early 2027.
Construction Schedule:
- Now through early March 2026: Work on lower/basement level.
- Late March to mid-June 2026: 2nd floor renovations; DEI and CRESS departments will temporarily relocate to the lower level.
- Through November 2026: 1st floor renovations, including Senior Center and Public Health Department.
- Through January 2027: Large activity room renovations.
Updates on phased construction and any program impacts will be provided by the Town and Senior Center. For more information, contact the Town Manager’s office at 413-259-3002.